Project Information
Project Name
TRA Houtong Slope Slide Monitoring
Project Location
Houtong, Ruifang District, New Taipei City
Software Platform
GeoSupply Automated Monitoring Cloud Platform
Project Details
A slope slide occurred at TRA's Ruifang–Houtong section, K12+233, on December 4 due to continuous heavy rain, disrupting both the east and west main lines. The east main line was reopened on December 13, restoring single-track bidirectional operation, while emergency repair work continues on the west main line.
To effectively monitor the slope and retaining wall conditions during construction, a total station is being used for continuous 24-hour measurement, with the automated monitoring system serving as a management reference — enabling timely and appropriate response measures whenever safety concerns arise, in support of train operating safety management.
Project Milestone
The east main line was reopened on December 13, restoring single-track bidirectional operation, while emergency repair work continued on the west main line.
Instruments
Leica TS15 Total Station
GeoSupply's Scope of Work
On-Site InstallationAutomated Monitoring SystemGeoSupply Cloud Platform
Outcome & Value
The total station provided 24-hour continuous monitoring data, serving as a safety management reference for slope and retaining wall conditions.